Estimate dozer push volume, hourly production rate, and daily earthmoving output.

[ Advertisement ]

Dozer Production Calculator

Select your dozer, enter push distance and conditions to get production estimates.

Cycle timeโ€”
Cycles per hourโ€”
Production per hourโ€”
Production per dayโ€”
โ€”
[ Advertisement ]

How Dozer Production is Calculated

Production depends on blade capacity, cycle time, material type, slope, and operator efficiency. The biggest variable is push distance โ€” doubling the distance roughly halves production.

Cycle Time Formula

Approximate cycle time = (push distance รท 200 fpm loaded) + (push distance รท 400 fpm return) + 0.3 min gear change. Actual speeds vary by machine and ground conditions.

Material Load Factors

Slot Dozing vs Open Dozing

Slot dozing (pushing in the same track) builds windrows on the sides, reducing spillage. It's 20-30% more efficient than open pushing. This calculator assumes open pushing โ€” add ~25% for slot dozing operations.

Typical Daily Production

Related Calculators

๐Ÿš› Truck Load ๐Ÿ“… Job Duration โ›ฝ Fuel Cost โ›๏ธ Cut & Fill Volume

Studying for the IUOE, Red Seal, or NCCER exam?

Complete study guides at dirtschool.ca โ†’